Events at the construction site

Events at the construction site
We would like to update you on the progress of our project.
Here is an overview of the recently completed work:
  • Sewage drainage
  • Rainwater drainage
  • We successfully carried out the removal of excess soil and topsoil.

Current works include:
  • Excavation, planting and gradual backfilling with subsequent compaction of sewage and storm sewers, water pipe discharge and water lines.
  • Provision of rainwater within the construction site.
  • Material is being transported, including water pipes, fittings, sewage pipes and manholes.
  • Connection of networks under the embankment is in progress.
  • We are preparing to connect the new water supply line.
 
We will continue to inform you about the further development of the project. Thank you for your support and patience.