Autumn sunny site inspection day.
10. 11. 2023
This year's very warm autumn weather favors the construction work, so everything is proceeding according to plan.
Transformer stations have been installed, road drainage has taken place, cable wiring preparation and installation of road curbs on axis A and part of axis B are ongoing. The main communication 'backbone' is taking clear shape, allowing the client to better envision the exact location of the entrance to their specific plot.